The Girders supporting the new mezzanine floor and principal roof struts have been installed. It was all hand to the pumps lifting the girders in place as it was not possible to get a crane to do the lifting owing to the confined space.
As the floor had to be laid before the reinstatement of the roof it is a worrying time as the floor is water resistant to a point but prolonged rain could ruin it.